Sand-colored single-story home with dark metal roofing, a wood entry door, broad concrete approach, drought-tolerant lawn and a sculptural piñon pine.

La Verkin Irrigation Water Reuse Project: What Changes for Your Yard

Ground broke on August 4, 2026, for a project that changes the water La Verkin uses on its lawns. Washington County Water Conservancy District crews are building a $12.5 million reuse system on the east side of the county. When it's done, La Verkin's secondary irrigation system will carry treated wastewater in place of the silty Virgin River water it has run on for generations. Completion is scheduled for March 2027, in time for the next irrigation season.

Cleaner sprinkler water is the part people in town will see. The bigger effect lands somewhere else. Every gallon of reuse water that goes on a La Verkin yard is a gallon of river water that can stay in the county's drinking supply. Starting next spring, the town's irrigation system becomes a working piece of how Washington County stores water to drink.

The route the water will take

St. George News coverage of the groundbreaking describes the parts of the system. Followed in order, the water's path goes like this:

  1. Household drains in La Verkin, Toquerville and Hurricane. All three communities send wastewater to the Ash Creek Special Service District's Confluence Park Water Reclamation Facility, which is designed to treat 1.5 million gallons a day.
  2. Treatment at Confluence Park. Bowen Collins & Associates, the plant's engineering firm, marked its official ribbon cutting in May 2026. The firm calls it the first project in Utah to use an aerobic granular sludge process, and says the plant produces Type I reuse water. Under Utah's rules, Type I water is the grade allowed for residential landscape irrigation.
  3. About 6,300 feet of ductile iron pipeline carrying treated water from the plant to the new storage site.
  4. A 7.1-million-gallon lined holding pond, where the reclaimed water is stored.
  5. A pump station that keeps pressure up in La Verkin's irrigation network.
  6. The city's existing secondary system, and from there the sprinklers and drip lines already in the ground.

The river stays in the picture. Any shortfall will still be made up with Virgin River water, but the exchange is designed to cut that demand down steadily over time.

What the county gets from a pond in La Verkin

The district and the City of La Verkin are splitting the $12.5 million cost. The Bureau of Reclamation provided funding plus environmental and cultural resource permitting help. It is a regional project in a small town, and the reason is the trade at its center.

Zach Renstrom, the district's general manager, called it a win-win. In his description, farmers and residents get irrigation water far less prone to the sediment that has long clogged ditches, sprinklers and drip systems. In return, more Virgin River water from above the La Verkin hot springs can be sent to district reservoirs such as Sand Hollow and Quail Creek, where it can eventually be treated as drinking water.

"The farmers are happy because they're going to get a better system," Renstrom said. "The nice thing from the water district standpoint is we're going to now have more water that we can put into Sand Hollow and Quail, and so we'll have more water in those reservoirs, which means we'll have more water that we can eventually treat and drink."

Where the water comes out of the river matters. According to the same report, the hot springs put about 109,000 tons of salt into the Virgin River, which flows on to the Colorado River. That has caused water quality and use problems downstream, especially for farmers, and the district and federal agencies have been working on it. River water taken above the springs is cleaner water for the reservoirs. La Verkin's yards can run on reuse water instead, so that upstream river water is free to go to drinking supplies.

The city already had a part in this. Mayor Kelly Wilson said La Verkin holds strong water rights on the Virgin River and has agreed to let unused irrigation water flow into district reservoirs for treatment. The pond gives that agreement physical infrastructure.

Sediment has been a La Verkin problem for a long time

Silt in the irrigation system has been part of La Verkin for longer than any pressurized pipe has existed in town. Washington County Commissioner Victor Iverson said at the groundbreaking that he grew up cleaning sediment out of the community's old open ditches. His father once served as water master for the LaVerkin Bench Canal Company.

"We've been dealing with sediment for a long time, and this pond will go a long ways toward solving our problems. More importantly, it'll increase the quality of the drinking water throughout the county … I believe that what we're doing here today is as important as those canals were." Victor Iverson, Washington County Commissioner

Iverson's quote moves from local ditches to county drinking water in the same breath, and the project does the same. KUTV's report on the groundbreaking called Virgin River water silt-laden and said sediment wears down sprinklers. It also reported the district's view that reuse water could support drip lines and timed sprinklers, which are the systems grit tends to clog.

Confluence Park was planned with more in mind than lawns. When KUTV covered the plant in January 2026, it reported that treated water would also be stored in winter to help meet summer demand. Plans called for it to fill the Chief Toquer reservoir and support water flow in Confluence Park and La Verkin Creek. The same wastewater from three towns is meant to fill a reservoir, keep a creek flowing and serve the local irrigation system.

What is still unsettled before March

The sources give a schedule and a design. They leave several practical questions open, and these are the ones that matter most to someone with a sprinkler controller in La Verkin.

  • How much reuse water at first. Mayor Wilson said the pond is expected to start with roughly 500,000 gallons a day of reuse water and grow over time. That is an expected starting volume, and river water will still fill any gap. The 2027 season will most likely run on a mix of reuse and river water, with the reuse share growing over time.
  • The city's own secondary-water project. The La Verkin City Council listed possible approval for a "secondary water project" to go out to bid on its September 16, 2026 agenda, and bidding was on the agenda again for the October 7, 2026 meeting. The agenda text doesn't describe the project's scope, location or cost. Nothing published so far ties it to the district's reuse pond, so the two should be treated as separate items until the city says otherwise.
  • Pipes, valves and labels. Utah's reuse rule requires purple pipe for new buried reuse lines in the public domain, plus reclaimed-water labels on valve covers. Where identification tape is installed, the rule specifies the wording "Caution: Treated Wastewater-Do Not Drink." The same rule says converting existing secondary lines to treated effluent is assessed case by case. So the statewide rule alone doesn't tell us what La Verkin's existing system will look like after the switch. No La Verkin-specific guidance has been published yet on signage or garden use.

The first piece of a much larger system

District engineer Trinity Stout called the La Verkin pond "the first project in our east-side reuse system," part of a years-long effort to make the most of the county's recycled water. Morgan Drake, the district's reuse program manager, said that even though the pond sits on the east side, the exchange will help secure drinking water for the whole county.

The next phase is bigger. A central reuse system, which was under environmental review with public comment open at the time of the groundbreaking, would include a pipeline of roughly 34 miles. It would carry reclaimed water from the St. George Regional Water Reclamation Facility to agricultural users as far east as Hurricane. The full Regional Reuse Purification System is projected to add about 24,000 acre-feet of water by 2046, which the district says is enough for roughly 40,000 homes. That system is part of more than $1 billion in planned infrastructure over the next two decades, funded by federal and state sources, impact fees on new growth and a low-interest state loan.

Compared with that plan, the La Verkin pond is small: 7.1 million gallons with a starting flow of about half a million gallons a day. It is also the first piece built. Officials described the whole system as designed to grow with population and to hold up in drought, since indoor wastewater is a fairly steady source. La Verkin's irrigation system is where the county will first put that design to work, with construction scheduled to finish in March 2027, ahead of the next irrigation season.

At Basalt Realty & Property Management, we track changes like this because they affect what owning a yard in La Verkin involves, from secondary-water hookups to the irrigation systems we manage on rental homes. If you have questions about how the switch to reuse water may affect a property you own or manage here, schedule a free consultation and we'll walk through what has been published so far.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.

Work With Us

At Basalt Realty, we help you buy, sell, and manage real estate across Southern Utah with expert guidance, local insight, and personalized service every step.

Follow Us on Instagram